Make a Donation!

Criterion Theatre

Criterion Big Build: Weekly Update
3rd June

Timing and Progress: 2.5 weeks behind schedule on agreed revised plan

Status against plan 

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
 
 
 
 
       
'Extension of time' certificate granted delaying contractor's completion date from 19th September to 16th October 2025. 

Contractor has stated that they still hope to finish by 16th October 2025.

 

Works Completed since last report (22nd August 2025)

 

Works Planned for Week Commencing 5th September 2025

 

 

Pictures showing that the plumbing installation has started and is planned to complete this week together with gas pipe replacement, also work has started to 'board out' the celing and most of this should be completed this week.

© 2025 Criterion Theatre Ltd
Registered UK 01643977 | Registered Charity 1161430