Criterion Big Build: Update
17th October

Timing and Progress: 2-3 weeks behind schedule on agreed revised plan

Status against plan 

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
         
'Extension of time' certificate granted delaying contractor's completion date from 19th September to 16th October 2025. 

Contractor has declared a further slip to 24th October 2025, but this is now unlikely to be achieved due to further delays. Likely completion date now w/c 3rd November 2025.

 

Works Completed since last report (10th October 2025)

 

Volunteers have continued their hard work with:

 

 

Works Planned for Week Commencing 20th October 2025

 

 

This weeks pictres show good progress as the contractors decorating has been completed and the toilet doors and tiles are starting to be fitted. Also showing some of our members hard at work sorting and tidying the auditorium and preparing the side foyer for decoration, including members of the  Criterion Board hard at work - please do contact secretary@criteriontheatre.co.uk if you would like to volunteer your time for upcoming activities to progress the redevelopment.