Contractor has declared a further slip to 24th October 2025.
Works Completed since last report (26th September 2025)
Works Planned for Week Commencing 6th October 2025
This weeks pictres show the ground floor windows and new automatic doors are now installed, together with extended paving areas outside. Inside after a very busy week of plastering, the internal walls and ceilings are now all plastered. Installation of lights, switches and sockets has now started.